Project Updates
Showing 11,901-11,920 of 32,380 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
11901EE/SHD/1st.Install for Constn. Emou/41First install for- Constn. of road with black topping from Ekou to Ekou Mulam Nepali Basti.PWDKangpokpi2018-19100%20/10/2022
11902MSPCLB21Construction of 132 kV link transmission line for evacuation of power from 400/132 kV SS at Thoubal to 132 kV SS at Moreh on 132 kV line from KakchingPOWER (MSPCL)KakchingXYZ65%20/10/2022
11903MSPCLB21Construction of 132 kV link transmission line for evacuation of power from 400/132 kV SS at Thoubal to 132 kV SS at Moreh on 132 kV line from KakchingPOWER (MSPCL)KakchingXYZ65%20/10/2022
11904MSPCLC50Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Khongjaron, Tamenglong District on turn key baPOWER (MSPCL)TamenglongA4020/10/2022
11905MSPCLC49Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basisPOWER (MSPCL)JiribamA4020/10/2022
11906MSPCLC49Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Gwakhal, Jiribam District on turn key basisPOWER (MSPCL)Jiribamxyz40%20/10/2022
11907SS/19-RengkaiHSS(Phase-I)-CCprStrengthening of School under Samagra Shiksha 2019-20 at Rengkai Hr. Sec. School, Churachandpur District, Manipur. (SH: Const. of 2(two) ACRs)Education (S)ChurachandpurNilInprogess20/10/2022
11908SS/19-RengkaiHSS(Phase-I)-CCprStrengthening of School under Samagra Shiksha 2019-20 at Rengkai Hr. Sec. School, Churachandpur District, Manipur. (SH: Const. of 2(two) ACRs)Education (S)ChurachandpurNilInprogess20/10/2022
11909MSPCLC48Installation of 2x5 MVA, 33/11 kV sub-station along with associated 33 kV line & related civil works at Kachai, Ukhrul District on turn key basisPOWER (MSPCL)Ukhrul13020/10/2022
11910PZL/In & around Pherzawl/6Improvement of road connectivity in and around Pherzawl District HQPWDPherzawlPhase I30%20/10/2022
11911PZL/In & around Pherzawl/6Improvement of road connectivity in and around Pherzawl District HQPWDPherzawl2019-2020100%20/10/2022
11912SS/D-2/19-LamlaiUPS-IM-EStrengthening of School under Samagra Shiksha, Manipur 2019-2020 at Lamlai Upper Primary School, Imphal East District, Manipur.Education (S)Imphal-EastnillUnder Construction20/10/2022
11913SS/D-2/19-LamlaiUPS-IM-EStrengthening of School under Samagra Shiksha, Manipur 2019-2020 at Lamlai Upper Primary School, Imphal East District, Manipur.Education (S)Imphal-EastnillUnder Construction20/10/2022
11914SS/D-2/19-LamlaiUPS-IM-EStrengthening of School under Samagra Shiksha, Manipur 2019-2020 at Lamlai Upper Primary School, Imphal East District, Manipur.Education (S)Imphal-EastnillUnder Construction20/10/2022
11915Moirangpurel High School SMDC 2019-2020Additional ClassroomEdu (S) - SSA & RMSAImphal-EastFinalCompleted19/10/2022
11916Moirangpurel High School SMDC 2019-2020Additional ClassroomEdu (S) - SSA & RMSAImphal-EastFinalCompleted19/10/2022
11917Moirangpurel High School SMDC 2019-2020Additional ClassroomEdu (S) - SSA & RMSAImphal-EastFinalCompleted19/10/2022
11918Moirangpurel High School SMDC 2019-2020Additional ClassroomEdu (S) - SSA & RMSAImphal-EastFinalCompleted19/10/2022
11919Moirangpurel High School SMDC 2019-2020Additional ClassroomEdu (S) - SSA & RMSAImphal-EastFinalCompleted19/10/2022
11920 Uripok Khamlangba Popular Primary SchoolConstruction of Boys Toilet Edu (S) - SSA & RMSAImphal-WestFinal installmentCompletion19/10/2022