Project Updates
Showing 4,841-4,860 of 31,875 items.
#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
4841UKL/Impvt of Raisheo Jn to Phalee Ukhrul /110Impvt of road from Raisheo Jn to Phalee village, Ukhrul districtPWDUkhrulPhase-I68% completed13/02/2025
4842SPT/Vaophea Junction to Kinafii colony/135Impvt of road from Vaophea Junction to Kinafii colony via RodziikhaoPWDSenapati1completed13/02/2025
4843SPT/Vaophea Junction to Kinafii colony/135Impvt of road from Vaophea Junction to Kinafii colony via RodziikhaoPWDSenapati1completed13/02/2025
4844SPT/Vaophea Junction to Kinafii colony/135Impvt of road from Vaophea Junction to Kinafii colony via RodziikhaoPWDSenapati1completed13/02/2025
4845SPT/Vaophea Junction to Kinafii colony/135Impvt of road from Vaophea Junction to Kinafii colony via RodziikhaoPWDSenapati1completed13/02/2025
4846SPT/Impvt of Napoukhovei to Fiimai gate/127Impvt of road from Napoukhovei to Fiimai gatePWDSenapati1completed13/02/2025
4847SPT/Impvt of Napoukhovei to Fiimai gate/127Impvt of road from Napoukhovei to Fiimai gatePWDSenapati1completed13/02/2025
4848SPT/Impvt of Napoukhovei to Fiimai gate/127Impvt of road from Napoukhovei to Fiimai gatePWDSenapati1completed13/02/2025
4849SPT/Impvt of Napoukhovei to Fiimai gate/127Impvt of road from Napoukhovei to Fiimai gatePWDSenapati1completed13/02/2025
4850SPT/Impvt of rd at Ngari Raidulomai lower/122Impvt of road at Ngari Raidulomai Lower villagePWDSenapati170% completed13/02/2025
4851SPT/Intra village road at Phaibung Khunou/124Impvt of intra village road at Phaibung Khunou villagePWDSenapati170% progress 13/02/2025
4852SPT/Intra village road at Phaibung Khunou/124Impvt of intra village road at Phaibung Khunou villagePWDSenapati170% progress 13/02/2025
4853SPT/Intra village road NH102A at Phaibung/123Impvt of intra village road connecting NH102A at Phaibung KhunouPWDSenapati1completed13/02/2025
4854SPT/Intra village road NH102A at Phaibung/123Impvt of intra village road connecting NH102A at Phaibung KhunouPWDSenapati1completed13/02/2025
4855SPT/Intra village road NH102A at Phaibung/123Impvt of intra village road connecting NH102A at Phaibung KhunouPWDSenapati1completed13/02/2025
4856SPT/Intra village road NH102A at Phaibung/123Impvt of intra village road connecting NH102A at Phaibung KhunouPWDSenapati1completed13/02/2025
4857SPT/Intra village road NH102A at Phaibung/123Impvt of intra village road connecting NH102A at Phaibung KhunouPWDSenapati1completed13/02/2025
4858KMJ/Impvt of road Riha to Thawai/Thoyee/273Impvt of road from Riha village to Thawai/Thoyee villagePWDKamjongphase 1completed13/02/2025
4859KMJ/Impvt of road Riha to Thawai/Thoyee/273Impvt of road from Riha village to Thawai/Thoyee villagePWDKamjongphase 1completed13/02/2025
4860KMJ/Impvt of road Riha to Thawai/Thoyee/273Impvt of road from Riha village to Thawai/Thoyee villagePWDKamjongphase 1completed13/02/2025