| 28921 | NH-I/GOM/2017-18/01 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 231.00 and km 245.00 during 2017-18 | PWD | Senapati | Completed | Completed | 18/08/2017 |
| 28922 | NH-I/GOM/2017-18/01 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 231.00 and km 245.00 during 2017-18 | PWD | Senapati | Completed | Completed | 18/08/2017 |
| 28923 | BRD/Heirok/7 | Construction of Bridge over Wangjing river at Heirok Chingdongpok | PWD | Thoubal | Begining phase | Ongoing | 18/08/2017 |
| 28924 | BRD/Heirok/7 | Construction of Bridge over Wangjing river at Heirok Chingdongpok | PWD | Thoubal | Begining phase | Ongoing | 18/08/2017 |
| 28925 | NH-I/GOM/2017-18/01 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 231.00 and km 245.00 during 2017-18 | PWD | Senapati | Completed | Completed | 18/08/2017 |
| 28926 | NH-I/GOM/2017-18/07 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 290.500 and km 311.000 during 2017-18 | PWD | Senapati | COMPLETED | COMPLETED | 18/08/2017 |
| 28927 | NH-I/GOM/2017-18/07 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 290.500 and km 311.000 during 2017-18 | PWD | Senapati | COMPLETED | COMPLETED | 18/08/2017 |
| 28928 | NH-I/GOM/2017-18/10 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 313.669 and km 315.400 during 2017-18 | PWD | Imphal-West | COMPLETED | COMPLETED | 18/08/2017 |
| 28929 | NH-I/GOM/2017-18/03 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 214.00 and km 231.00 during 2017-18 | PWD | Senapati | Completed | Completed | 18/08/2017 |
| 28930 | NH-I/GOM/2017-18/03 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 214.00 and km 231.00 during 2017-18 | PWD | Senapati | Completed | Completed | 18/08/2017 |
| 28931 | NH-I/GOM/2017-18/02 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 245.00 and km 260.00 during 2017-18 | PWD | Senapati | COMPLETED | COMPLETED | 18/08/2017 |
| 28932 | NH-I/GOM/2017-18/02 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 245.00 and km 260.00 during 2017-18 | PWD | Senapati | Completed | Completed | 18/08/2017 |
| 28933 | NH-I/GOM/2017-18/05 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 269.00 and km 282.00 during 2017-18 | PWD | Kangpokpi | Completed | Completed | 18/08/2017 |
| 28934 | NH-I/GOM/2017-18/06 | Resectioning of road side drain i/c removal of raised side berm at selected stretches between km 282.00 and km 290.500 during 2017-18 | PWD | Kangpokpi | COMPLETED | COMPLETED | 18/08/2017 |
| 28935 | FOR/CONST/ZOO/01 | SAMBAR ENCLOSURE | FOREST | Imphal-West | NIL | Completed | 18/08/2017 |
| 28936 | BRD/Salanthong/19 | Construction of Salanthong Bridge over Imphal River (SH: Protection work of Retaining Wall from 3m to 14m). | PWD | Imphal-East | 1 | completed | 16/08/2017 |
| 28937 | BRD/Salanthong/19 | Construction of Salanthong Bridge over Imphal River (SH: Protection work of Retaining Wall from 3m to 14m). | PWD | Imphal-East | 1 | completed | 16/08/2017 |
| 28938 | BRD/Salanthong/19 | Construction of Salanthong Bridge over Imphal River (SH: Protection work of Retaining Wall from 3m to 14m). | PWD | Imphal-East | 1 | completed | 16/08/2017 |
| 28939 | BRD/Salanthong/19 | Construction of Salanthong Bridge over Imphal River (SH: Protection work of Retaining Wall from 3m to 14m). | PWD | Imphal-East | 1 | completed | 16/08/2017 |
| 28940 | 04_shijaoxygen | Establishment of Shija Regional Oxygen Plant and Generation Unit, Langol Imphal Manipur | Planning Department | Imphal-West | 1 instalment | Shija Regional Oxygen Generation Unit | 11/08/2017 |