#Project CodeProject NameDepartmentDistrictPhaseProgress StatusApprove Date
     
28481FOR/CONST/ZOO/02DEER/SANGAI ENCLOSUREFORESTImphal-WestNILConstruction completed02/12/2017
28482POL-50Construction of infrastructure for Litan Police Station, Ukhrul District under Modernisation, 2013-14 (8)HOMEUkhrulNo100percent completed01/12/2017
28483POL-48Construction of infrastructure for Yaingangpokpi Police Station, Imphal East District under Modernisation, 2013-14 (6)HOMEImphal-EastSingle100% completed01/12/2017
28484POL-38Construction of main Police Stations (1st Phase) at Keibul Lamjao Police Station, Bishnupur District.HOMEBishnupurSingle phase100% completed01/12/2017
28485POL-31Construction of main Police Stations (1st Phase) at Yaingangpokpi Police Station, Imphal East District.HOMEImphal-EastSingle100% completed01/12/2017
28486FOR/CONST/TML/GIMConstruction of Eco Hut at LukhambiFORESTTamenglongCompletedCompleted30/11/2017
28487FOR/CONST/TML/GIMConstruction of Eco Hut at LukhambiFORESTTamenglongCompletedCompleted30/11/2017
28488FOR/CONST/TML/MPConstruction of multipurpose hall at langkhongFORESTTamenglongIn progressIn progress30/11/2017
28489FOR/CONST/TML/MPConstruction of multipurpose hall at langkhongFORESTTamenglongIn progressIn progress30/11/2017
28490FOR/CONST/TML/MPConstruction of multipurpose hall at langkhongFORESTTamenglongIn progressIn progress30/11/2017
28491MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28492MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28493MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28494MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28495MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28496MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28497MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28498MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28499MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017
28500MSPCLB3INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT MOREH WITH ASSOCIATED 132 kV LINE AND RELATED CIVIL WORKPOWER (MSPCL)ChandelX70%30/11/2017