22801MSPCLB2INSTALLATION OF 2x12.5 MVA, 132/33 kV S/S AT THANLON WITH ASSOCIATED LINEPOWER (MSPCL)Churachandpurcompleted100%26/12/2019
22802MSPCLB15Installation of 1x20 MVA transformer at Yaingangpokpi 132/33 kV SS for replacement of old transformer on turn keyPOWER (MSPCL)Imphal-EastCompleteComplete26/12/2019
22803MSPCLB15Installation of 1x20 MVA transformer at Yaingangpokpi 132/33 kV SS for replacement of old transformer on turn keyPOWER (MSPCL)Imphal-EastCompleteComplete26/12/2019
22804MSPCLB15Installation of 1x20 MVA transformer at Yaingangpokpi 132/33 kV SS for replacement of old transformer on turn keyPOWER (MSPCL)Imphal-EastCompleteComplete26/12/2019
22805MSPCLC7Installation of 2x1 MVA, 33/11 kV Sub-Station at HenglepPOWER (MSPCL)ChurachandpurComplete100%26/12/2019
22806WRD-FCW-119Works approved under Work Advisory Board 2019-20Water Resources Department (WRD)Others1Complete24/12/2019
22807WRD-FCW-119Works approved under Work Advisory Board 2019-20Water Resources Department (WRD)Others1Complete24/12/2019
22808WRD-FCW-119Works approved under Work Advisory Board 2019-20Water Resources Department (WRD)Others1Complete24/12/2019
22809WRD-FCW-119Works approved under Work Advisory Board 2019-20Water Resources Department (WRD)Others1Completed24/12/2019
22810WRD-FCW-119Works approved under Work Advisory Board 2019-20Water Resources Department (WRD)Others1Complete24/12/2019
22811NEC1Integrated approach for enhancing ecosystem services of Nungkot Sarbei Machengpat at Andro, Imphal East, ManipurEnvironment and CCImphal-EastPhase2Ongoing23/12/2019
22812NEC1Integrated approach for enhancing ecosystem services of Nungkot Sarbei Machengpat at Andro, Imphal East, ManipurEnvironment and CCImphal-EastPhase2Ongoing23/12/2019
22813NEC1Integrated approach for enhancing ecosystem services of Nungkot Sarbei Machengpat at Andro, Imphal East, ManipurEnvironment and CCImphal-EastPhase2Ongoing23/12/2019
22814KMJ/Infra/1Infrastructure Development of Kamjong,Kamjong District,Manipur.PWDKamjong2nd phaseIn progress23/12/2019
22815KMJ/Infra/1Infrastructure Development of Kamjong,Kamjong District,Manipur.PWDKamjong2nd phaseIn progress23/12/2019
22816KMJ/Infra/1Infrastructure Development of Kamjong,Kamjong District,Manipur.PWDKamjong2nd phaseIn progress23/12/2019
22817MSPCLA2Construction of 400 kV Line on Double circuit towers initially charged at 132 kV from Yurembam to Thoubal via NambolPOWER (MSPCL)Imphal-WestXyz95%23/12/2019
22818MSPCLA2Construction of 400 kV Line on Double circuit towers initially charged at 132 kV from Yurembam to Thoubal via NambolPOWER (MSPCL)Imphal-WestXyz95%23/12/2019
22819MSPCLA2Construction of 400 kV Line on Double circuit towers initially charged at 132 kV from Yurembam to Thoubal via NambolPOWER (MSPCL)Imphal-WestRTrial23/12/2019
22820EE/HS/AFS/Re-constn. of Rd. from Wangoi../42.Re-constn. of Rd. from (i) Wangoi to Nambul Rver, (ii) Naorem to Nambul River & Internal roads of Govindagram, Wangoi.PWDImphal-WestPhase 1In progress23/12/2019