Progress
 
 
Project Details
DAR-2020-000657
WRD-FCW-139
Clearance of floating phum/water hyacinth from Lilakhong Stream at Langthabal, Imphal West District, Manipur
06/06/2020
Water Resources Department (WRD)
Imphal-West
11.00
11.00
State Plan
Complete
1
24.743792,93.915126
Progress Update : 12/11/2020
Complete
1
FCD-2
24.743792,93.915126
24.74376236,93.91501019
0.012150391840963
0
Clearance of floating phum/water hyacinth along Lilakhong stream at Langthabal, Imphal West.

Progress Update : 09/11/2020
Complete
1
FCD-2
24.743792,93.915126
24.7502188,93.9204393
0.89359205900613
0
Clearance of floating phum/water hyacinth from Lilakhong stream at Langthabal, Imphal West, Manipur.

Progress Update : 09/11/2020
Complete
1
FCD-2
24.743792,93.915126
24.74723423,93.92214187
0.80523673746348
0
Clearance of floating phum/water hyacinth from Lilakhong stream at Langthabal, Imphal West, Manipur.