Progress
 
 
Project Details
DAR-2025-000117
UKL_PHED_SASCI_SRC_AUG_UKL
Source Augmentation of the existing Ukhrul Town Water Supply Scheme
19/11/2024
PHED
Ukhrul
600.00
0.00
SASCI
completed
final phase
25.125333, 94.456843
Design, drawing and construction of office building, intake arrangement, check dams, reservoir, pumping station and procurement of pipes and pumps complete.
Progress Update : 30/04/2026
completed
final phase
panshangh
25.125333, 94.456843
25.1254322,94.4566392
0.023293262282248
0
Retaining wall at ground sump

Progress Update : 30/04/2026
completed
final phase
panshangh
25.125333, 94.456843
25.1245578,94.4571927
0.093106190536829
0
check dams

Progress Update : 29/04/2026
completed
final phase
panshangh
25.125333, 94.456843
25.0948429,94.3609896
10.228814671849
0
office building

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.125065,94.4566533
0.035392997674346
0
Ground sump

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1249933,94.4570017
0.041010954574903
0
RCC drain at pumping site

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1248617,94.4566517
0.055830246865827
0
angle iron fancing around pump house chowkidar quater and pump house

Progress Update : 28/04/2026
completed
Final
panshangh
25.125333, 94.456843
25.1256683,94.45668
0.04073324884061
0
Toilet near chowkidar Quater

Progress Update : 28/04/2026
completed
Final
panshangh
25.125333, 94.456843
25.1272933,94.4547367
0.30408639496173
0
Chowkidar Quater

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.12544,94.4536933
0.31729997064155
0
relocation of pipe line

Progress Update : 28/04/2026
completed
Final
panshangh
25.125333, 94.456843
25.12533,94.453695
0.31690602237414
0
approch road

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.12555,94.4539967
0.2875478624595
0
pump reservoir 1 lakh litter

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.12465,94.455665
0.14082067574349
0
improvement of approch road

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.12121,94.458555
0.48976136595854
0
intake 1

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.121235,94.4584483
0.48346464278541
0
CHECK DAM 1

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1210284,94.4583867
0.50322390773441
0
CHECK DAM 2

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1207918,94.4587631
0.54066864826191
0
check dam 3

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1214467,94.4583633
0.45841948549494
0
INTAKE 2

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.121455,94.45832
0.45611007443512
0
COLLECTION CHAMBER

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1258917,94.4566967
0.063843510072199
0
INSTALLATION OF ELECTRIC PUMP SET

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.125695,94.4561833
0.077656703029333
0
installation of diesel generator

Progress Update : 28/04/2026
completed
1
panshangh
25.125333, 94.456843
25.1286633,94.4554867
0.39466448537336
0
Installation of transformer

Progress Update : 05/06/2025
work in progress
phase 1
panshangh
25.125333, 94.456843
25.12552,94.4567614
0.02235633820674
0
pump house

Progress Update : 05/06/2025
completed
final phase
panshangh
25.125333, 94.456843
25.1250033,94.4567733
0.037324561333774
0
Ground sump

Progress Update : 05/06/2025
completed
final phase
panshangh
25.125333, 94.456843
25.124538,94.4571765
0.094556678517651
0
check dam 4

Progress Update : 05/06/2025
work in progress
phase 1
panshangh
25.125333, 94.456843
25.1253966,94.456737
0.01280122509996
0
retaining wall

Progress Update : 05/06/2025
completed
final phase
panshangh
25.125333, 94.456843
25.1256192,94.454295
0.25847063201802
0
pump reservoir

Progress Update : 05/06/2025
completed
final
panshangh
25.125333, 94.456843
25.0948169,94.3608666
10.241457755793
0
office building

Progress Update : 05/06/2025
completed
final
panshangh
25.125333, 94.456843
25.0945322,94.3608667
10.251990138729
0
boundary wall

Progress Update : 05/06/2025
work in progress
final phase
panshangh
25.125333, 94.456843
25.1272717,94.4547817
0.29921023285531
0
Chowdikar quarter

Progress Update : 21/02/2025
Completed
Phase I
panshangh
25.125333, 94.456843
25.094563,94.3609065
10.247068215668
0
C/O Compound wall with Gate

Progress Update : 21/02/2025
Work in progress
Phase I
panshangh
25.125333, 94.456843
25.0947796,94.3610292
10.227391224866
0
Construction of office building

Progress Update : 21/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.12113,94.45845
0.49453936990615
0
C/O check dam 5

Progress Update : 21/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.1210015,94.4586115
0.5134709759302
0
C/O check dam 6

Progress Update : 21/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.1209393,94.4586066
0.51979479078098
0
C/O check dam 7

Progress Update : 21/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.1208606,94.4586776
0.53047362746084
0
C/O check dam 8

Progress Update : 21/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.1286806,94.4555135
0.39554885596001
0
Transformer

Progress Update : 20/02/2025
work in progress
Phase I
panshangh
25.125333, 94.456843
25.1250817,94.4568317
0.02796495621209
0
Levelling for Ground sump

Progress Update : 20/02/2025
work in progress
Phase I
panshangh
25.125333, 94.456843
25.1293799,94.4556561
0.46556603820798
0
Power supply Line

Progress Update : 20/02/2025
work in progress
Phase I
panshangh
25.125333, 94.456843
25.1273251,94.4547423
0.3062411516273
0
Earthwork in foundation for Chowkidar Quarter cum Godown

Progress Update : 20/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.1256267,94.4543633
0.25175547411812
0
C/O Pump reservoir

Progress Update : 20/02/2025
Completed
phase I
panshangh
25.125333, 94.456843
25.1213947,94.4582799
0.46117158383215
0
C/O Collection Chamber

Progress Update : 20/02/2025
work in progress
phase I
panshangh
25.125333, 94.456843
25.1211259,94.4584548
0.49512833227366
0
C/O intake weir

Progress Update : 20/02/2025
work in progress
Phase I
panshangh
25.125333, 94.456843
25.1211212,94.4585025
0.49721491496878
0
C/O check dam 9

Progress Update : 20/02/2025
Completed
phase I
panshangh
25.125333, 94.456843
25.1286407,94.4497439
0.80373314846374
0
Approach road